Heatcraft Refrigeration Products 25000102 Benutzerhandbuch

Seite von 36
8  
 
 
 
 
Part # 25000102
In systems equipped with capacity control compressors, 
or where multiple compressors are used with one or more 
compressors cycled off for capacity control, double suction 
risers should be installed. See Figure 6 below. The two 
lines should be sized so that the total cross-section area 
is equivalent to the cross section area of a single riser that 
would have both satisfactory gas velocity and acceptable 
pressure drop at maximum load conditions. The two lines 
normally are different in size, with the larger line trapped as 
shown. The smaller line must be sized to provide adequate 
velocities and acceptable pressure drop when the entire 
minimum load is carried in the smaller riser.
In  operation,  at  maximum  load  conditions  gas  and 
entrained  oil  will  be  flowing  through  both  risers.  At 
minimum load conditions, the gas velocity will not be 
high enough to carry oil up both risers. The entrained oil 
will drop out of the refrigerant gas flow and accumulate 
in the “P” trap forming a liquid seal. This will force all of the 
flow up the smaller riser, there by raising the velocity and 
assuring oil circulation through the system.
When connecting more than one suction line to a main 
trunk line, connect each branch line with an inverted trap. 
See Figure 7 below:
Straight runs should be supported near each end.
Long runs require additional supports.
A general guide is:
3/8” to 7/8” every 5 feet
1-1/8” to 1-3/8” every 7 feet
1-5/8” to 2-1/8” every 10 feet
When changing directions, supports should be placed a 
maximum of 2 feet in each direction.
Piping attached to a vibrating object (such as a compressor 
or compressor base) must be supported in such a manner 
that will not restrict the movement of the vibrating object. 
Rigid mounting will fatigue the copper tubing.
Use only a suitable silver solder alloy on suction and liquid 
lines.
Limit the soldering paste or flux to the minimum required 
to prevent contamination of the solder joint internally. Flux 
only the male portion of the connection, never the female. 
After brazing, remove excess flux.




Installation and Operations Manual
When  brazing  refrigerant  lines,  an  inert  gas  should 
be passed through the line at low pressure to prevent 
scaling and oxidation inside the tubing. Dry nitrogen is 
preferred.
Use long radius ell’s for lower pressure drop.
Provide  expansion  loops  in  long  straight  refrigerant 
lines that are subject to expansion and contraction. See 
Expansion Loops in this manual for more information.
Refrigerant Line Insulation
Insulate suction lines from the evaporators to the parallel 
unit  with  minimum  3/4”  thickness  closed-cell  type 
insulation on low temperature circuits. Insulate suction 
lines on medium temperature circuits with minimum 1/2” 
thick insulation to prevent condensation.
Long liquid lines run in areas exposed to high temperatures 
should be fully insulated with minimum 1/2” insulation.
Suction  and  liquid  lines  should  never  be  taped  or       
soldered together.
Refrigerant Line Support
Strap  and  support  tubing  to  prevent  excessive  line 
vibration and noise. All tubing clamps should have an 
insulating material (i.e. Hydra Sorb bushing) to prevent 
metal to metal contact.

Figure 6. Double Suction Risers
Figure 7. Inverted Trap
Figure 8. Pipe Support