Chapter 19.  Switch Stacks 
 
ProSafe Managed Switch 
4. 
Continue with the boot of operational code.
5. 
Once the stack is up, download the saved configuration back to the master. This 
configuration should then be automatically propagated to all members of the stack.
Copy Master Firmware to a Stack Member (Web Interface)
1. 
Select System > Management > Basic > Stack Configuration. A screen similar to the 
following displays.
2. 
In the Copy Master Firmware to Unit list, select 2.
3. 
Click Apply.
Configure a Stacking Port as an Ethernet Port
Figure 38. Configuring a stacking port as an Ethernet port
Follow these steps to set up the topology:
1. 
Insert the AX742 into the I/O module on the switch. 
2. 
Configure the switch A and B as described in the following instructions.
3. 
Connect the AX 742 with stack cable.
4. 
Reboot Switch A and Switch B.
AX742
2/0/28
AX742
1/0/28