Switch Stacks 
489
 Managed Switches
b.  In the Reboot Unit No. menu, select 2.
c.  Click Apply.
The switch reboots.
Add, Remove, or Replace a Stack Member
You can manage an operating stack.
Add Switches to an Operating Stack
To add new switches to an operating stack:
1. 
Make sure that the redundant stack connection is functional.
All stack members must be connected in a logical ring.
2. 
Preconfigure any new switches.
3. 
Power off all new switches that must join the stack.
CAUTION:
If you cable one or more powered-on switches to the stack, the existing 
stack and the new switches assume that two stacks are merging. They 
elect a single, new stack master, and you cannot specify which switch 
becomes the new master. All stack members assume the configuration 
that is based on the new stack master. Stack members change their stack 
member numbers to the lowest available numbers. 
4. 
Install the new switches in the rack. 
This procedure assumes installation below the bottom-most switch, or above the 