FINAL OPERATING CHECKS
OPL MICRO CONTROL TUMBLER
Refer to OPL micro-control section to check control for 
proper operation.
MANUAL DUAL TIMER TUMBLER 
Refer to Figure 13
.
1. Set the TEMPERATURE selector to the desired 
temperature, and set the DRYING and COOLING 
selectors to maximum.
2. Press the PUSH-TO-START button in and hold it in 
for approximately three seconds. The motor will 
start, the heat system will come on and the DRYING 
indicator will light.
3. During the drying period the DRYING selector 
rotates counterclockwise. When the DRYING 
selector reaches “0” the heat system will shut off, the 
DRYING indicator will go out and the COOLING 
indicator will light.
During the cooling period the COOLING selector rotates 
to the left. When the COOLING selector reaches “0” the 
motor will stop and the COOLING indicator will go out 
indicating the end of the cycle.
COIN-OPERATED TUMBLER
Refer to Figure 14
.
1. Set the TEMPERATURE selector to the desired 
temperature.
2. Insert required number of coins in the coin slot and 
turn the knob fully clockwise and release it. The 
RUN indicator (option) will light.
For Coin Slide Models — Place required number of 
coins in coin slide and push slide in as far as possible, 
then release.
3. Press the PUSH-TO-START button in and hold it in 
for approximately three seconds. The motor will start 
and the heat circuit will come on.
4. An automatic preset 2-1/2 minute cool-down period 
occurs near the end of the cycle. During this period 
the heat system is off and encompassing air circulates 
through the load to cool it.
5. When the coin metered time expires, the cycle is 
completed.