Central Heat Option
 
Use high temperature silicone to seal the 
block-off plate to the unit. If necessary drill 
extra holes in the plate and the unit and 
secure with extra screws.
Note: Make sure the block-off plate is fl ush and 
fastened tightly to the WarmHearth.
Important: A tight joint between ma-
sonry and the fi replace is necessary 
to prevent heat from rolling up the 
front to the Face Header.
INSTALLING YOUR
CENTRAL HEATING
SYSTEM
The WarmHearth may be used  as a central 
forced air heating unit by adding ducting and 
a fan.
Materials Required:
1) 
Blower requirements: see Options 2 and 
3  in section "F) Installing the Blower Sys-
tems"
Flex Vent
5)  Install the connector collar into the unit 
making sure it is pushed all the way down.  
Reach through the upper  louver opening 
and snip and bend out the lower edge of the 
collar in at least 4 places inside the fi replace 
with pliers so it can't be pulled out. 
INSTALLATION
IMPORTANT:  Make sure the front edge of 
the collar is fl ush with the front edge of the 
air vent frame.
Note: The fl ex duct can easily be trimmed 
shorter or stretched longer.
Note: Termination boxes require a
 
 
14-1/2"W x 15-3/8"H opening in com-
bustible materials.
8)  Locate and install the lower air vent next.  
A 7-3/4" x 7-3/4" opening is required to fi t  
the frame that is supplied. The vent must be 
installed in the chase and should be within 
12" of the fl oor.
WARNING: Lower air vent MUST 
be installed in all applications, 
otherwise serious overheating of 
the chase may result.
9)  Fasten the block-off plate to the WarmHearth 
using the existing holes that normally secure 
the louvers, using the louver screws.  Make 
sure the top edge is up.  
6)  Slide the collar into the fl ex duct. secure with 
an adjustable clamp. Snip and bend out the 
outer edge of the collar in at least 4 places 
inside the frame so it can't be pulled out. 
7)  Drill holes or use nails to attach the Vent 
Frame to the wall. Note: holes in frame are 
used to attach the Vent cover. 
2) 
Metal ducting, grills and distribution boxes.  
(Installer Supplied)
3) 
Ducting is tested at 1 in. clearance to fram-
ing for the fi rst 6 feet and 1/2 in. thereafter 
and no stand-offs are required. All ducting 
should be insulated to reduce heat loss.
CAUTION: Blowers must meet 
specifi cations listed (refer to Install-
ing the Blower Systems section). A 
home fi re may result from the use 
of substitute parts.
Installation
1)  Remove screws from one of the vent hole 
covers "A" (but not both) on top of the 
WarmHearth.
2)  Take one way duct vent pipe and rotate 
in hole to cut through 4 in. of insulation.  
Remove insulation from pipe.
3)  Remove screws on cover "B" and slide it to 
the back.
4)  Install the one way valve making sure it is 
pushed all the way down.  Shutters should