Maintenance Object Repair Procedures 
9-724
DUP-CHL (Duplication Interface) 
9
Replacing Duplication Channel Components
The SPE Duplication Channel consists of a Duplication Interface circuit pack 
(DUPINT) in the active SPE, a DUPINT in the standby SPE, and an 
interconnecting cable. The following sections contain step-by-step procedures 
for replacing each of these components. DUPINT replacement must be done on 
the standby SPE to prevent loss of service.
If replacement of standby DUPINT circuit pack does not repair the Duplication 
Channel, replace the DUPINT circuit pack on the active SPE. If replacement of 
both of these circuit packs does not repair the Duplication Channel, replace the 
interconnecting cable.
Replacing the STANDBY Duplication Interface 
(DUPINT) Circuit Pack
This procedure is used after a test duplication-interface long displays a failure 
for at least one of the tests that indict the standby DUPINT. The procedure to 
interchange the active DUPINT to the standby mode also uses this procedure.
1. Use the busyout spe-standby command to lower the standby State of 
Health to partially functional to prevent an unwanted interchange during 
replacement and testing of the standby DUPINT.
2. Manually lock the active SPE. by moving the SPE select switches located 
on the front of the DUPINT circuit packs to positions where they are both 
selecting the current active SPE.
3. Whenever locking the SPE, 
always verify that the active PPN Tone/Clock is 
in the active SPE carrier 
before doing any repair activity on the standby 
SPE carrier such as powering down. Enter status port-network 1 to 
check which clock is active. Remove power from the standby SPE carrier 
by pulling the power cords located on both sides of the carrier. 
Power 
must be removed from the standby carrier in order for the replacement 
DUPINT to initialize properly.
4. Set the SPE-select switch on the new DUPINT circuit pack to the same 
position as the circuit pack you are going to replace. Then remove and 
replace the defective circuit pack.
!
CAUTION:
The new standby DUPINT must have its SPE Select switch set to lock 
the currently active carrier. The switch should be in the same 
position as the removed circuit pack.
5. Apply power to the standby SPE carrier.