9-1166
PDMODULE (Processor Data Module) TDMODULE (Trunk Data Module) 
9
n. Make sure the data module is connected and operating properly. Check 
for faulty wiring. If necessary, reduce the length of the cable between the 
data module and the switch to 5000 ft for 24-gauge wire or 4000 ft for 
24-gauge wire. Refer to 
DEFINITY Communications System Generic 1 and 
3 - Installation and Test, 555-230-104.
If the problem still exists, replace the circuit pack. Once the problem has 
been resolved, the alarm will be retired in 60 minutes (90 min for error 
1537). (These error counters use the leaky bucket mechanism.)
The DA module is not phantom-powered from the port. Thus when it is in 
linked mode, its range is limited by the Italtel digital phone’s limit: 0.7 Km 
(2300) ft on 26-gauge wire or 1.8 Km (5900) ft on 22-gauge (0.6 mm) wire. 
If in stand-alone mode, it is limited by the maximum length of loop allowed 
from the Digital Line Interface (DLI) component: up to 3.5 Km (2 miles) on 
22-gauge (0.6 mm) wire.
System Technician-Demanded Tests: Descriptions 
and Error Codes
Always investigate tests in the order presented in the table below. By clearing 
error codes associated with the 
Data Module Internal Looparound Test, for 
example, you may also clear errors generated from other tests in the testing 
sequence.
NPE Crosstalk Test (#9)
The NPE Crosstalk Test verifies that this port’s NPE channel talks on the selected 
time slot and never crosses over to time slots reserved for other connections. If 
the NPE is not working correctly, one-way and noisy connections may be 
observed. If a secondary data module is assigned, it is tested after the primary 
data module. If either test fails, both data modules are taken out of service. This 
test usually run only during the long test sequence and takes about 20 to 30 
seconds to complete.
Order of Investigation
Short Test 
Sequence
Long Test 
Sequence
D/ND
1
1.
D = Destructive; ND = Nondestructive
 Data Module Internal Looparound Test (#175)
X
ND
Digital Port Board Network Processing Element Crosstalk 
Test (#9)
X
ND
Port Circuit Information Channel and Control Channel 
Looparound Test (#13)
X
ND
Data Module Audits Test (#17)
X
X