6.4.7 
Required Power-Off Sequence 
The required BIOS sequence for removing power from the drive is as follows: 
Step 1: Issue one of the following commands. 
   
 
Standby 
     
 
Standby immediate 
   
 
Sleep 
Note: 
Do not use the Flush Cache command for the power off sequence because this command does not 
invoke Unload 
Step 2: Wait until the Command Complete status is returned.    In a typical case 350 ms are required for the 
command to finish completion; however, the BIOS time out value needs to be 30 seconds considering error 
recovery time.   
Step 3: Terminate power to HDD.