SharkRack 42U User Manual
SharkRack Enclosure Installation Guide
ID-00210-000
REV D, ECO2773
Page 27 of 46
Installing a Grounding Kit
Step Detail
Grounding points are provided on the various cabinet
components so that each component can be electrically
bonded to the frame.
components so that each component can be electrically
bonded to the frame.
Detail A:
Shows how to route the grounding cables through the
frame of the cabinet. Connection (1) attaches to either of
the door assemblies. Connection (2) attaches to the side
panel
frame of the cabinet. Connection (1) attaches to either of
the door assemblies. Connection (2) attaches to the side
panel
Detail B:
Shows where connection (2) attaches to the corner of the
Side Panel
Side Panel
Detail C:
Shows how to route the grounding cable to the top panel.
Detail D:
Shows the door grounding cable being routed through the
face of the corner post (reverse side of Detail A).
face of the corner post (reverse side of Detail A).
Figure 27
Grounding Points
42U X 37DP Cabinet Shown