Emerson 4015 User Manual

Page of 64
Installation Instructions 
IM584000300 
Spec. No. 584000300 (Model 4015-X003) 
Issue AB, April 3, 2013 
 
 
Chapter 2. Installing the System 
Page 9 
 
This document is property of Emerson Network Power, Energy Systems, North America, Inc. and contains confidential and proprietary information owned by Emerson Network Power, Energy 
Systems, North America, Inc.  Any copying, use, or disclosure of it without the written permission of Emerson Network Power, Energy Systems, North America, Inc. is strictly prohibited. 
INSPECTING THE EQUIPMENT AND 
STORING FOR DELAYED INSTALLATIONS 
Inspecting the Equipment 
Compare the contents of the shipment with the bill of lading.  Report any missing items to 
the carrier and your local Emerson representative immediately. 
While the DC Power System is still on the truck, inspect the equipment and shipping 
container(s) for any signs of damage or mishandling. 
As the equipment is moved off the truck and unpacked, visually examine the DC Power 
System for transit damage. 
Do not attempt to install the system if damage is apparent. 
If any damage is noted, file a damage claim with the shipping agency within 24 hours and 
contact Emerson Network Power (number located on last pages of this document) to 
inform them of the damage claim and the condition of the equipment. 
Storing for Delayed Installation 
If the equipment will not be installed immediately, it must be stored indoors where the 
humidity is no higher than 95%.  The storage area must protect the DC Power System 
from excessive moisture. 
SECURING THE IT RACK TO THE FLOOR 
Secure the IT rack to the floor per site requirements.  Refer also to the General 
Requirements
 section at the beginning of this chapter. 
Factory Integrated Systems (List R1, R2) 
For systems factory furnished in an IT rack (List R1, R2), position and secure the 
Emerson Network Power DCM IT Rack to the floor as follows. 
Procedure 
1)  Use at least two people when moving the IT rack. 
2)  Using a pallet jack or forklift, move the IT rack on its pallet to the installation 
location. 
3)  Cut the shrink wrap and remove all packaging. 
4)  Remove the lag bolts securing each shipping bracket to the shipping pallet.  
There is one bracket at each corner of the IT rack (each bracket has two lag 
bolts). 
5)  Use a pallet jack or forklift to raise the IT rack off the shipping pallet. 
6)  Slide the shipping pallet out from under the IT rack. 
7)  The IT rack may be positioned for installation either with the forklift or by rolling 
the cabinet on its casters.  If the casters are to be used to move the cabinet, 
prepare the IT rack for rolling as follows. 
a)  Set the IT rack on the floor. 
b)  Using a hex wrench, lower each leveling feet until the IT rack is not resting 
on the shipping brackets. 
c)  Remove the hex bolts securing each shipping bracket to the IT rack.