3.4.1 Project Schedule
3.4.1.1 Estimated Project Schedule
The following is an estimated schedule for Project 2 - VSE to MVS conversion.
The project may begin upon completion of the Inventory Determination task of
Project 1, estimated to be on or about June 1, 1996, and will last approximately
nine (9) months with a switchover to MVS after approximately eight (8) months.
Table 3. Nine M o n t h Project
Month Number
Month Initial
1
2
3
4
5
6
7
8
9
J
J
A
S
O
N
D
J
F
Phase 1 - Specifications
**
**
**
*
Phase 2 - Custom Modifications of CORTEX-MS
*
**
**
**
Phase 3 - First Trial Conversions: Online and
Batch Appl
*
*
Phase 4a - MVS Tests & Repetitive
Conversions : Online
Phase 4b - MVS Tests & Repetitive
Conversions : Batch
*
**
**
**
*
**
**
**
*
Phase 5 - Actual Conversion and Switchover
*
Phase 6 - Assisted MVS Operations
**
3.4.1.2 Estimated Schedule for CNV Responsibilities
The following is an estimated schedule for CNV responsibilities. The actual
schedule will be determined at project start.
Table 4. CNV Responsibilities
Month Number
Month Initial
1
2
3
4
5
6
7
8
9
J
J
A
S
O
N
D
J
F
01 - Manage CNV Conversion Responsibilities
**
**
**
**
**
**
**
**
**
02 - Provide Technical Leadership
*
*
*
*
*
03 - Receive and Validate the Conversion
I n v e n t o r y
*
*
*
*
*
*
*
*
*
04 - Develop the Conversion Specifications
**
**
**
**
*
05 - Custom Modify CORTEX-MS and
Proprietary Tools
*
**
**
**
**
06 - Perform Manual Conversion Activities
*
*
*
07 - Perform Automated Mass Conversions
*
*
*
*
*
*
*
*
08 - Assist with Setup of MVS Automated
Operations Tools
*
*
*
09 - Participate in Online Applications Testing
**
**
**
*
10 - Perform Batch Applications Testing
*
**
**
**
*
11 - Participate in Applications Switchover to
MVS
*
**
12 - Support Initial MVS Operations
**