IBM OS/390 User Manual

Page of 673
3.4.2 Project Plan Example
The actual schedule will be determined at Project 2 start, based on the
completion of the Project 1 Inventory Determination completion date, the
expected switchover date, and any potential conflicts with ABC
s processing.
3.4.2.1 Project Plan - Summary
Task Name
ID
Projected
Actual
Start
End
Start
End
Preparation Phases
01
01/09/98
05/10/98
Application Inventory
02
01/09/98
03/10/98
Specifications
03
02/01/98
05/03/98
Customization
04
02/15/98
05/10/98
Conversion Phases
05
04/26/98
09/21/98
Trial Conversion
06
04/26/98
09/21/98
Online Testing
07
04/26/98
07/26/98
Batch Testing
08
05/10/98
09/13/98
Production Testing
09
08/16/98
09/21/98
Implementation Phases
10
09/01/98
10/15/98
Actual Conversion & Switchover
11
09/01/98
10/23/98
Initial MVS Operations
12
09/20/98
10/23/98
Migration Completion
10/23/98
10/23/98
56