3.4.2.2 Project Plan - Details
ID
Task Name
Projected
Actual
Start
End
Start
End
01
Project Approval
01/09/98
01/09/98
02
Application Inventory
01/09/98
08/24/98
03
Initial & Inventory Supplies
01/09/98
03/10/98
04
0 % Missing
03/10/98
03/10/98
05
General Inventory Supply Every 3 Weeks
03/10/98
08/24/98
06
Less than 2% Missing
02/01/98
02/01/98
07
Project Planning
01/09/98
09/21/98
08
Project Plan
01/09/98
02/13/98
09
Develop Project Plan
01/09/98
01/23/98
10
Present Project Plan
01/23/98
01/23/98
11
Review & Complete Project Plan
01/23/98
02/13/98
12
Online Test Plan & Scripts
02/14/98
04/26/98
13
Provide Online Test Orientation
02/14/98
02/14/98
14
Develop Online Test Plan & Scripts
02/15/98
04/26/98
15
Review Online Test Plan & Scripts
02/15/98
04/26/98
16
Batch Test Plan & Scripts
03/28/98
06/07/98
17
Provide Batch Test Orientation
03/28/98
03/28/98
18
Develop Batch Test Plan & Scripts
03/29/98
06/07/98
19
Review Batch Test Plan & Scripts
04/12/98
06/07/98
20
Switchover Plan
07/05/98
09/21/98
21
Develop Switchover Plan
07/05/98
07/18/98
22
Provide Switchover Test Orientation
07/19/98
07/19/98
23
Complete & Refine Switchover Plan
07/19/98
09/21/98
24
Online Application Conversion
02/01/98
04/26/98
25
COBOL Program Conversion
02/01/98
04/26/98
26
Develop COBOL Online Conversion
Specifications
02/01/98
04/26/98
27
Develop Automated COBOL Online
Conversion
02/15/98
04/26/98
28
Perform Manual COBOL Online
Conversion
04/12/98
04/26/98
29
Map, Table, Data Conversion
03/01/98
04/26/98
30
Migrate CICS Maps
03/01/98
04/26/98
31
Setup CICS Application Tables
03/29/98
04/26/98
32
Migrate CICS Application Files &
Databases
03/29/98
04/26/98
33
Online Tests Can Start
04/26/98
04/26/98
34
Online Application Tests & Corrections
04/26/98
08/30/98
35
Participate in Online Initialization Tests
04/26/98
05/10/98
36
Perform Online Sample Tests
05/10/98
06/07/98
37
Online Application Tests Can Start
06/07/98
06/07/98
58
VSE to OS/390 Migration Workbook