Installing the Hardware
Installing the System in the Rack
4.3
Installing the System in the Rack
V
CAUTION!
For safety reasons, at least two people are required to install the 
PRIMERGY BX600 S3 basic unit because of its weight and size.
Please observe the safety precautions and references to rack instal-
lation in the 
The rack may tip over if more than one unit is removed at the same 
time.
Requirements of the Rack
The rack systems from Fujitsu Technology Solutions GmbH (PRIMECENTER 
rack; DataCenter rack) fully support the installation of the PRIMERGY server 
systems. Installation in the common rack systems of other manufacturers (3rd-
party rack
) is supported to a large degree.
To accommodate the ventilation concept and ensure proper ventilation of the 
components in the rack, any unused areas must be closed using dummy covers.
The unit is connected to the power supply via an external distribution board, a 
32 A power distribution unit (PDU) or a UPS device. 
The main features of the rack systems from Fujitsu Technology Solutions GmbH 
are:
PRIMECENTER/DataCenter Rack
Frontally bolted rails.
The rails have a linear alignment option to also allow adjustment to different 
rack depths.
Extended cable management within the lateral rack area.
The following applies to rack systems from third-party manufacturers: