 Installing earthquake bracing
NN43021-310
Standard 02.01
December 2007
5
Abandon the hole if you should hit a reinforcing bar or the hole breaks 
through. A minimum of two diagonally opposite anchors are required for 
this application.
6
Remove any debris from the hole with a blowout bulb or compressed air. 
Use a vacuum cleaner to dispose of the debris.
7
Insert the anchors into the holes. Use the manufacturer’s setting tool to 
install each anchor flush with the surface of the concrete. Use the Hilti 
HST 12.7 mm (1/2 in.) setting tool, manufacturer part # 000329805 or 
equivalent.
8
Position each column over the anchors.
9
Insert bolt, metal washer, and shoulder washer into the pedestal hole, as 
shown in the Figure 124 on 
On the far side of the pedestal 
flange, thread a plastic washer, a metal washer, and the nut onto the bolt. 
Insert the bolt into the concrete anchor.
10 Tighten the nut to the pedestal flange and torque it to 34 J (25 ft-lb) using 
a 20 mm (3/4 in.) socket wrench. Do not overtighten.
11 Repeat steps 8 to 11 for remaining bolts.
End of Procedure