DEFINITY Enterprise Communications Server Release 8.2
Upgrades and Additions for R8r  
555-233-115  
Issue 1
April 2000
Multicarrier G2 Universal Module to R8r EPN 
5-106
Critical Reliability 
5
Remove Power-Failure Ground Strap
Remove the ground strap from the power-failure transfer unit.
Boot the Release 8 System
1. Connect the management terminal to the “TERMINAL” connector behind 
PPN control carrier “A,” or install the G3-MA according to the “Set Up 
G3-MA” chapter of 
DEFINITY Communications System Generic 3 
Management Applications 
 Operations, 585-229-202.
2. Insert the translation cards in the TN794 faceplates.
3. At each EPN power distribution unit, set the main circuit breaker to ON.
4. At the PPN power distribution unit, set the main circuit breaker to ON.
5. The system performs the reset level 4 rebooting process, loading the 
default system translations from the translation cards. This takes 8 to 11 
minutes.
6. Get the order number of the upgrade and call the regional CSA to request 
an “init” login so the right-to-use options can be enabled.
7. To use Access Security Gateway (ASG), see