Lucent Technologies 555-233-115 User Manual

Page of 502
DEFINITY Enterprise Communications Server Release 8.2
Upgrades and Additions for R8r  
555-233-115  
Issue 1
April 2000
Adding or Removing Cabinet Hardware 
6-118
Add a Switch Node Carrier (High or Critical Reliability) 
6
10. If a switch node carrier is being installed in the “D” position of an EPN, 
verify that the ZAHF4 TDM/LAN bus terminator is installed at slot “02” of 
expansion control carrier “A”. See 
If a switch node carrier is being installed in the “E” position of an EPN, 
verify that the ZAHF4 TDM/LAN bus terminator is installed at slot “21” of 
port carrier “D.”
For a PPN, install the ZAHF4 TDM/LAN bus terminator at slot “01” of switch 
node carrier “E.”
11. Install the front trim plates on the “D” carrier.
12. Install the new power units into the carrier. One 649A is installed on the left 
and right sides of the carrier.
13. Connect the power cords to the power units. The power cords are the 
white cables equipped with plugs that are run through the slots in the front 
of each carrier.
Install Circuit Packs
1. Install the new circuit packs into carrier “D.” Use the decal and the 
upgrade configuration document (provided with the equipment) as a 
guide.
2. Install circuit pack blanks in slots not equipped with circuit packs.
Table 6-10.
TDM/LAN Connections
“J” Number
Carrier Type
LHS Slot
RHS Slot
J58890BB L1
Port
21
02
J58890BB L2
Port
21
01
J58890BB L3
Port
21
01
J58890AP
Control
21
02