Monessen Hearth CDVR33N/PV7 User Manual

Page of 60
74D3000
18
BLDV7 Series Gas Fireplace
Vent InStaLLatIon 
Sealing  vent  pipe  and  firestop  gaps  with  high  tem-
perature sealant will restrict cold air being drawn in 
around fireplace.
Step 7
Guide  the  vent  terminations  4”  and  7”  collard  into  their 
respective vent pipes. Double check that the vent pipes 
overlap  the  collars  by  ”  (51  mm).  Secure  the  termina-
tion  to  the  wall  with  screws  provided  and  caulk  around 
the wall plate to weatherproof. As an alternative to screw-
ing the termination directly to the wall, you may also use 
expanding plugs or an approved exterior construction ad-
hesive. You may also attach the termination with screws 
through the inner body into the 4” vent pipe, however for 
this method, you must extend the 4” pipe approximately 
6” (15 mm) beyond the outer face of the wall.
Support horizontal pipes every 36” (914 
mm) with metal pipe straps.
VertICaL SIDewaLL InStaLLatIon - 
FLex Vent pIpe
 
note: The 40” (1016 mm) flex vent is used for 90° bend 
after  a  straight  vertical  section  (1"  min.)  then  out  the 
back wall.
Follow Steps 1 - 3 on Page 17.
Step 4
Install the four (4) spacer springs on the 4” flex vent pipe. 
When  installing  the  spacer  springs    around  the  4”  pipe, 
stretch  the  spring  to  approximately  15”  (381  mm),  wrap 
the spring around the pipe and interlock the ends of the 
spacer spring approximately ” (51 mm). Measure 18C\v” 
(476 mm) from the end of the pipe. Place the next spring 
5”  (17  mm)  from  the  previously  installed  spring.  Place 
the next spring 6” (15 mm) from the last spring. Finally 
place  the  last  spring  1”  (305  mm)  from  the  last  spring 
installed. Figure 19
Step 5
Install the 4” (10 mm) flex vent pipe to the appliance col-
lar as described on Page 13. Secure the end with the first 
spring 18C\v” (476 mm) from the flex pipe end to the unit.
Step 6
Slide the 7” (178 mm) flex vent pipe over the 4” flex vent 
pipe and secure the 7” collar as described on Page 13.
Step 7
Bend the flex pipe horizontal so the bottom of the horizon-
tal pipe measure 18Z\x” (470 mm) from the top of the unit 
immediately after the 90° formation. Figure 20. Be sure to 
follow the 1/” (13 mm) rise in a 1” (305 mm) horizontal 
run rule.
Step 8
Install the 4” flex then 7” flex to the termination.
12"
(305  mm)
6"
(152 mm)
5"
(127 mm)
186M"
(476 mm)
FP1474
spacer springs
4/04  djt
4" Flex 
Vent Pipe
Spacer 
Spring
FP1474
Figure 19 - 
Install Spacer Springs
1856O" 
(470 mm)
FP1475
flex 90 bend
4/04  djt
Figure 20 - 
Bend Flex Vent at 
90° so Horizontal 
Portion is 18
Z\x" (470 
mm) Off Top of Unit
FP1475
BeLow GraDe InStaLLatIon
When it is not possible to meet the required vent terminal 
clearances  of  1”  (305  mm)  above  grade  level,  a  snor-
kel kit is recommended. It allows installation depth down 
to  7”  (178  mm)  below  grade  level.  The  7”  (178  mm)  is 
measured from the center of the horizontal vent pipe as it 
penetrates through the wall.
ensure the sidewall venting clearances are observed. 
If venting system is installed below ground, we rec-
ommend  a  window  well  with  adequate  and  proper 
drainage to be installed around the termination area.
If installing a snorkel, a minimum 4” (610 mm) vertical 
rise is necessary. The maximum horizontal  run with the 
4”  vertical  pipe  is  36”  (914  mm). This  measurement  is 
taken from the collar of the fireplace (or transition elbow) 
to the face of the exterior wall. See the Sidewall Venting 
Graph for extended horizontal run if the vertical exceeds 
4” (610 mm).
1.  Establish  vent  hole  through  the  wall.  Page  17,  Figure 
16