APC galaxy 9000 User Manual

Page of 40
34006451EN/AC
 - Page 9
Characteristics
Installation comprising modular UPSs with an external maintenance bypass
The table below serves as an example for an installation with up to four modular UPSs with an external maintenance bypass.
– for installations with redundant units, take into account only the units required to supply the load power 
(e.g. for an installation made up of 3 parallel-connected rectifier-inverter cubicles, one being redundant, only 2 units are used 
to determine the currents on the maintenance bypass line and the load, and the cross-sectional areas of cables);
– this table has been drawn up for rated phase-to-phase Mains 2 and load voltages of 415 V and full rated load with a power 
factor of 0.9. For voltages of 380 or 400 V, multiply the indicated currents by 1.09 and 1.04 respectively, then modify the cable 
cross-sections accordingly if necessary. 
The cable cross-sections in this table are for the parts illustrated in bold on the following block diagrams (installation example, 
figure 3);
– important. In an installation with an external maintenance bypass, the power cables between each UPS and the 
upstream protection devices must be the same length
. The same holds for the power cables between each UPS cubicle 
and the external maintenance bypass.
rated 
inverter 
output
in kVA
number of
parallel-connected
inverters
total UPS
rated output
in kVA
mains 2 or load
line current 
in Amps
cable
cross-section (1)
in mm²
800
2
1600
2310
Please consult us*
3
2400
3465
Please consult us*
4
3200
4620
Please consult us*
900
2
1800
2598
Please consult us*
3
2700
3897
Please consult us*
4
3600
5196
Please consult us*
(
1) cable cross-sections are given for copper conductors of the U1000 R02V type (increase by 30 % for aluminium conductors). 
They are calculated according to permissible temperature rise and allow for line voltage drops over a maximum length of 100 m.  
For greater lengths, the cross-sections should be chosen to limit voltage drops to 3 %.
* NF C 15-100 authorizes a maximum of 4 cables per phase.
Fig. 3
maintenance Bypass cubicle
mains 1
inverter 1
inverter 2
inverter 3
load
mains 2
mains 1
mains 2
mains 1
mains 2