PVI Industries quickdraw pv500-24 User Manual

Page of 4
PV500-24  03-99 
 
Section 24 
1
INSTALLATION & MAINTENANCE MANUAL FOR 
QuickDraw
 
INSTANTANEOUS 
ENERGY:  WATER TO WATER 
U-TUBE SINGLE-WALL & DOUBLE-WALL HEAT EXCHANGERS 
 
 
 
TYPICAL CONSTRUCTION 
FIGURE 24-1 
 
1.  U-tube Heat Exchanger 
9.  Boiler Water Temperature Gauge * 
2.  Boiler Water Inlet 
10.  Tridicator * 
3.  Boiler Water Pump 
11.  Flow Switch * 
4.  Control Enclosure 
12.  Relief Valve (AGA optional) 
5.  Intratank Circulator 
13.  Tank Purge Valve * 
6.  Potable Water Inlet 
14.  Boiler Water Outlet 
7.  Potable Water Outlet 
15.  Check Valve 
8.  Tank Drain 
 
 
 
 
* Optional 
 
 
 
 
 
 
 
CAUTION: TEMPERATURES HIGHER THAN 125
°F. INCREASE THE RISK OF SCALD INJURY! 
 
IMPORTANT: Clearances for servicing and inspection are 18” at top, sides and rear and a 