Emerson Switch 3ADTS User Manual

Page of 8
ASCO 3ATS, 3ADTS, 3NTS, 3NDTS 
 
Installation Manual 
Page 2 
ASCO Power Technologies 
381333-406 
Line Connections 
Refer to the wiring diagram provided with the transfer switch.  
All wiring must be made in accordance with the National 
Electrical Code and local codes. 
 
 
 
De-energize the conductors before making any line 
or auxiliary circuit connections.  Be sure that the 
Normal and Emergency line connections are in 
proper phase rotation.  Place the engine generator 
starting control in the OFF position.  Make sure 
engine generator is not in operation. 
Testing Power Conductors 
Do not connect the power conductors to the transfer switch 
until they are tested.  Installing power cables in conduit, cable 
troughs, and ceiling-suspended hangers often requires 
considerable force.  The pulling of cables can damage 
insulation and stretch or break the conductor’s strands.  For 
this reason, after the cables are pulled into position, and before 
they are connected, they should be tested to verify that they 
are not defective or have been damaged during installation. 
Connecting Power Cables 
After the power cables have been tested, connect them to the 
appropriate terminal lugs on the transfer switch as shown on 
the wiring diagram provided with the transfer switch.  Make 
sure that the lugs provided are suitable for use with the cables 
being installed.  Standard terminal lugs are solderless screw 
type and will accept the wire sizes listed on the drawings 
provided with the transfer switch.  Be careful when stripping 
insulation from the cables, avoid nicking or ringing the 
conductor.  Remove surface oxides from cables by cleaning 
with a wire brush.  When aluminum cable is used, apply joint 
compound to conductors.  Tighten cable lugs to the torque 
specified on rating label. 
Harnesses 
The transfer switch is connected to the left side of the 
controller by a plug-in harness (two plugs). 
Auxiliary Circuits 
Connect auxiliary circuit wires to appropriate terminals on the 
transfer switch as shown on the wiring diagram. 
Controller Ground 
A grounding wire must be connected to the controller’s lower 
left mounting stud.  Because the controller is mounted on the 
enclosure door, a conductive strap must be used between the 
enclosure and the door.  This connection provides proper 
grounding which does not rely upon the door hinges. 
Engine Starting Contacts 
The engine control contact connections (if used) are located on 
the transfer switch for 3ATS & 3NTS or in the upper right 
side of the enclosure for 3ADTS & 3NDTS.  Connect signal 
wires to appropriate terminals as specified in Table A and 
shown in Figure 1. 
Table A.  Engine Start Connections. 
When normal 
source fails 
Terminals on 
transfer switch 
contact closes 
TB1 and TB2 
contact opens 
TB1 and TB3 
 
 
 
Figure 1. Engine start and auxiliary circuit terminal block. 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Figure 2.  Main contact position indicators on right side. 
TB 
    DANGER 
 
 
 
 
!
window 
indicators 
OPEN or
CLOSED 
Emergency 
contacts 
Normal 
contacts