Westinghouse WGR050LP076 Installation Instruction

Page of 60
11 
 
 
                                                                                  WHL-001 REV. 12.17.14 
 
When raising the heater, fully support the entire bottom of the water heater. 
 
Locate or protect the heater so it cannot be damaged by a moving vehicle. 
E. EXHAUST VENT AND INTAKE PIPE 
The heater is rated ANSI Z21.10.3 Category IV (pressurized vent, likely to form condensate in the vent) and requires a special vent 
system designed for pressurized venting. 
 
NOTE: The venting options described here (and further detailed in Venting, Part 5 in this manual) are the lone venting options 
approved for this water heater. Failure to vent the water heater in accordance with the provided venting instructions will void 
the warranty. 
 
 
Failure to vent the water heater properly will result in serious personal injury or death. 
 
 
Do not attempt to vent this water heater by any means other than those described in this manual. Doing so will void the warranty, and 
may result in severe personal injury or death. 
 
 
Vents must be properly supported. Heater exhaust and intake connections are not designed to carry heavy weight. Vent support 
brackets must be within 1’ of the heater and the balance at 4’ intervals. Heater must be readily accessible for visual inspection for the 
first 3’ from the heater. 
 
 
The exhaust discharged by this water heater may be very hot. Avoid touching or other direct contact with the exhaust gases or the vent 
termination assembly. Doing so may result in product damage, severe personal injury, or death. 
1. DIRECT VENT INSTALLATION OF EXHAUST AND INTAKE 
If installing a direct vent option, combustion air must be drawn from the outdoors directly into the water heater intake, and exhaust must 
terminate outside. There are three basic direct vent options detailed in this manual: 1. Side Wall Venting, 2. Roof Venting, and 3. 
Unbalanced Venting. 
 
Be sure to locate the heater such that the exhaust vent and intake piping can be routed through the building and properly terminated. 
Different vent terminals can be used to simplify and eliminate multiple penetrations in the building structure (see Optional Equipment in 
Venting Section). The exhaust vent and intake piping lengths, routing and termination methods must all comply with the methods and 
limits given in the Venting section, Part 5 of this manual. 
 
When installing a combustion air intake from outdoors, care must be taken to utilize uncontaminated combustion air. To prevent 
combustion air contamination, see Table 1
 
2. INDOOR COMBUSTION AIR INSTALLATION IN CONFINED OR UNCONFINED SPACE 
This heater requires fresh, uncontaminated air for safe operation and must be installed in a mechanical room where there is adequate 
combustion and ventilating air. NOTE: To prevent combustion air contamination, see Table 1 
 
Combustion air from the indoor space can be used if the space has adequate area or when air is provided through a duct or louver to 
supply sufficient combustion air based on the water heater input. Never obstruct the supply of combustion air to the water heater. 
If the water heater is installed in areas where indoor air is contaminated (see Table 1) it is imperative that the water heater be installed 
as direct vent so that all combustion air is taken directly from the outdoors into the water heater intake connection. 
 
Unconfined space is space with volume greater than 50 cubic feet per 1,000 Btu/hour (4.8 cubic meters per kW) of the total input 
rating of all fuel-burning appliances installed in that space. Rooms connected directly to this space, through openings not furnished with 
doors, are considered part of the space. Se
, p. 34 for details. 
 
Confined space is space with volume less than 50 cubic feet per 1,000 Btu/hour (4.8 cubic meters per kW) of the total input rating of 
all fuel-burning appliances installed in that space. Rooms connected directly to this space, through openings not furnished with doors, 
are considered part of the space. 
 
When drawing combustion air from inside a conventionally constructed building to a confined space, such space should be provided 
with two permanent openings
: one located 6” (15 cm) below the space ceiling, the other 6” (15cm) above the space floor. Each opening 
should have a free area of one square inch per 1,000 Btu/hr (22cm
2
/kW) of the total input of all appliances in the space, but not less 
than 100 square inches (645cm
2
).