4 Functions of the Operator Module
This chapter describes the operation of the PLC via the operator 
module. An example of commissioning operations is used to 
explain the individual functions. 
Initial PLC startup 
When the power supply is switched on, the UPS device closes the 
Power Fail circuit. The PLC operating system is started and the 
”Waiting for Signal” message appears on the display of the oper-
ator module. The STOP, RUN and SF (SF = Central error) LEDs of 
the operator module are not lit. The STOP LED lights up and the SF 
LED light up after a few seconds.
If there is no program in the PLC, and the operating mode selector 
switch (OMS) is set to STOP, the display will show the following 
information after a few seconds:
The STOP and SF LEDs are lit. When the SF LED is lit, this indicates 
that the PLC did not find a bootable program during the startup. 
The ! in the display indicates that the PLC is in STOP status.
Clear the messages first of all:
X
Choose menu item MAIN MENU r DIAGNOSTICS CLEAR.
This will display the CLEAR menu.
X
Instead of No select Yes by turning the MSS.
X
Press the MSS.
X
Press the MSS once more after ENTER is displayed.
The SF LED will go out and the exclamation mark will be cleared.
X
Return to the basic menu.
You can now load a program into the PLC using XSoft or select the 
main menu using the menu selector switch.
X
Press the MSS when the cursor flashes in front of the MAIN 
MENU menu item.
Your are now in the main menu and can select the individual menu 
items.
Loading the program into the PLC
You can transfer a compiled program such as the program 
TESTPRO from the PC to the PLC.
Requirement: The OMS must be set to STOP or RUN-P.
X
Choose Online r Login in the XSoft programming software.
If there is no program in the PLC, the following window will 
appear:
X
Click on Yes.
This will confirm the storing of a bootable version of the program 
in the working memory. The display will change:
If there is a program in the working memory already, it will be 
overwritten after the confirmation.
X
Click on Yes. The program name will change in the display.
Create a bootable version of this program:
X
Click on Create Boot Project in the Online menu when you have 
logged into the PLC.
The program is loaded into the program memory switched to 
bootable status and is activated automatically. This is what is 
required to start the program after the power supply is switched 
on.
h
The basic operating principles of the PLC are described in 
the Chapter “Menu Overview of the Operator Module” on 
Page 41.
Time, event message, PLC status
PLC status (irrespective of OMS)
Program content (no program in PLC)
Menu entry
! Indicates an event
S = STOP (event)
17:10:37 !S
STOP
PROG:
???
>MAIN MENU
Figure 63:
Loading a new program
Figure 64:
Loading new program when the old one was present
17:29:23
!S
STOP
TESTPRO.PRO
>MAIN MENU