Ariston A/23 MFFI Manual De Usuario

Descargar
Página de 28
22
B023
4.1
Changing the Type of
Gas
The boiler can be converted to use either methane (natural) gas (G20) or
LPG (G30 - G31) by an Authorised Service Centre.
The operations that must be performed are the following:
1. Replace the jets on the main burner (see table in section 4);
2. Adjust the maximum and minimum thermal capacity values for the boiler
(see table in section 4);
3. Replace the gas rating plate;
4. Adjust the maximum thermal power setting;
5. Adjust the soft-light feature;
6. Adjust the ignition delay feature for the heating system (can be set from
0 to 2 mins.).
CATEGORY II2H3+
Methane Gas
Liquid Butane Gas
Liquid Propane Gas
G20
G30
G31
Recommended Soft-Light Pressure
(mbar)
5-5.5
17 - 18
18 - 19
It is recommended that the following checks be made on the boiler at
least once a year:
1 - Check the seals for the water connections; replacement of any faulty seals.
2 - Check the gas seals; replacement of any faulty gas seals.
3 - Visual check of the entire unit.
4 - Visual check of the combustion process and cleaning of the burners if
needed.
5 - If called for by check no. 3, dismantling and cleaning of the combustion
chamber.
6 - If called for by check no. 4, dismantling and cleaning of the injectors.
7 - Visual check of the primary  heat exchanger:
- check for overheating in the blade assembly;
-  clean the exhaust fan if needed.
8 - Adjustment of the flow rate of the gas: flow rate for lighting, partial load and 
full load.
9 - Check of the heating safety systems:
- safety device for maximum temperature;
- safety device for maximum pressure.
10 - Check of the gas safety systems:
- safety device for lack of gas or flame (detection electrode);
- safety device for gas cock.
11 - Check of the electrical connection (make sure it complies with the
instructions in the manual).
12 - Check of domestic hot water production efficiency (delivery rate and tem-
perature)
13 - Check of the general performance of the unit.
14 - General check of the discharge/ventilation of the combustion by-
products.
5.
MAINTENANCE