14
Brocade DCX 8510-4 Backbone Hardware Reference Manual
53-1002177-05
Preparing for Brocade DCX 8510-4 installation
2
Preparing for Brocade DCX 8510-4 installation
NOTE
Read the safety notices before installation (
).
Read 
 to plan for meeting power supply standards before installing the 
chassis.
Read 
 to plan for cable management.
TABLE 2
Installation tasks, time, and items required
Installation task
Time estimate
Items required
Site preparation and unpacking Brocade 
DCX 8510-4
30 minutes
1/2-in. socket wrench (to remove pallet bolts).
#2 Phillips screwdriver
(for cable management comb).
Pallet jack.
Hydraulic lift or assisted lift, able to raise to a 
minimum of 140 cm (55 in.), with a minimum 
capacity of 113 kg (250 lb). The Brocade DCX 
8510-4 weighs 68 kg (150 lb) with four 
FC16-48 port cards installed (192 ports). 
Installing rack mount kit or 
port side exhaust kit
30 minutes
 Refer to the one or more of the following if you 
are mounting the Brocade DCX 8510-4 in a 
rack:
Brocade Port Side Exhaust Kit Installation 
Procedure
Brocade DCX 8510-4, DCX-4S Mid-Mount Rack 
Kit Installation Procedure
 or
Brocade DCX 8510-4, DCX-4S Rack Kit 
Installation Procedure.
Mounting and securing Brocade DCX 
8510-4 in rack
30 minutes
Installing power cables and powering on 
the Brocade DCX 8510-4
20 minutes
Power cables (provided in the Brocade DCX 
8510-4 accessory kit).
Establishing serial connection, logging on 
to Brocade DCX 8510-4, and configuring IP 
addresses
20 minutes
Serial cable (provided in the accessory kit).
Workstation computer with a serial port or 
terminal server port and a terminal emulator 
application (such as HyperTerminal).
Ethernet IP addresses for the Brocade DCX 
8510-4 chassis and for both control processor 
blades: total three addresses.
Installing an Ethernet cable, opening a 
Telnet session, and configuring the 
Brocade DCX 8510-4 domain ID, date and 
time, and additional system parameters. 
Verify and back up configuration.
20 minutes
Ethernet cabling (optional) for Telnet access.
Refer to the Fabric OS Administrator’s Guide.
Installing transceivers as needed
20 minutes (longer 
if using high-density 
port blades)
SFP+, mSFP, and QSFP optical transceivers as 
needed.
Attaching fiber-optic cables, cable ties, and 
cable guides
2-3 hours
Fiber-optic cables, cable ties, and cable comb.