Cisco AVS 3120 Application Velocity System Hardware Installation Guide
OL-11805-01
Chapter 2      Preparing for Installation
Preparing Your Site for Installation
Creating a Safe Environment
Follow these guidelines to create a safe operating environment:
Keep tools and chassis components off of the floor and away from foot traffic.
Clear the area of possible hazards, such as moist floors, ungrounded power extension cables, and 
missing safety grounds.
Keep the area around the chassis free from dust and foreign conductive material (such as metal 
flakes from nearby construction activity).
AC Power Requirements
Ensure that the plug-socket combination is accessible at all times, because it serves as the main 
disconnecting device. Refer to 
 for the AVS 3120 power requirements.
Warning
This product requires short-circuit (overcurrent) protection, to be provided as part of the building 
installation. Install only in accordance with national and local wiring regulations. 
Statement 1045
Power Supply Guidelines
Follow these guidelines for power supplies:
Check the power at the site before installing the chassis to ensure that the power is free of spikes 
and noise. Install a power conditioner, if necessary, to ensure proper voltages and power levels in 
the source voltage.
Install proper grounding for the site to avoid damage from lightning and power surges.
The chassis does not have a user-selectable operating range. Refer to the label on the chassis for the 
correct AC-input power requirement.
Several types of AC-input power supply cords are available; make sure that you have the correct type 
for your site.
Install a UPS for your site.
Cabling
Use the cables in the accessory kit to connect the AVS 3120 console port to a console or computer that 
is running a console program. In addition to using the console cable, use the provided standard Ethernet 
cable to connect the AVS 3120 to your network. Refer to 
 for information 
on cable requirements.