Tower Start-Up
Among  other  sources,  outbreaks  of  Legionnaires’  Disease  have
reportedly been traced to cooling towers. Maintenance and water 
treatment procedures that prevent amplification and dissemination
of Legionella and other airborne bacteria should be formulated and 
implemented BEFORE systems are operated and continued regularly 
thereafter to avoid the risk of sickness or death.
Water System:
1.   New installations should be cleaned and treated with biocides by a 
water treatment expert before startup. 
2.   Remove any and all accumulated debris from tower. Pay particular 
attention to inside areas of cold water basin, hot water basins, louvers 
and drift eliminators. Make sure that cold water suction screens are 
clear and properly installed.
3.   Fill the water system to an approximate depth of 7
1
2
" (192 mm) in 
the depressed area of the cold water basin at the air inlet side of the 
tower. This is the recommended operating water level. Adjust the float 
valve so that it is 75% open at that level. Continue filling the system 
until the water reaches a level approximately 
1
8
" (3 mm) below the lip 
of the overflow.
If tower is equipped with a standard suction connection, vent ac-
cumulated air from the top of the suction hood by removing one or 
both tap screws provided at that location. Replace these tap screws 
when venting is complete.
 
4.   Completely open hot water flow control valve(s). Start your pump(s) 
and observe system operation. Since the water system external to the 
tower will have been filled only to the level achieved in the cold water 
basin, a certain amount of “pump-down” of the basin water level will 
occur before water completes the circuit and begins to fall from the 
fill. The amount of initial pump-down may be insufficient to cause the 
float valve to open. However, you can check its operation by pressing 
down on the operating lever to which the stem of the float valve is 
attached. 
    Some trial-and-error adjustment of the float valve may be required to 
Note
Operation
 
Warning