Radiance Direct Vent Gas Heater
20012697
Minimum Height
Above Roof
ST934
minimum height
6/07
   
Minimum  
  Roof Pitch 
Height
  Flat to 7/12 
1’0”
  Over 7/12 to 8/12 
1’6”
  Over 8/12 to 8/12 
2’0”
  Over 9/12 to 10/12 
2’6”
  Over 10/12 to 11/12 
3’3”
  Over 11/12 to 12/12 
4’0”
  Over 12/12 to 14/12 
5’0”
  Over 14/12 to 16/12 
6’0”
  Over 16/12 to 18/12 
7’0”
  Over 18/12 to 20/12 
7’6”
  Over 20/12 to 21/12 
8’0”
Fig. 45  Minimum Height Above Roof Requirements
the assembled pipe to the appliance. Determine and 
mark the location of where the support collar will be at-
tached to the pipe. Disconnect and remove assembled 
pipe. Attach the support collar per Step 10 (where 
marked) and reinstall assembly. This is due to limited 
space within the cathedral ceiling support box. Install 
any required offset supports.
11.  Add lengths of pipe and firestop as necessary 
until assembly extends to a point above the roof which 
complies with local code requirements for minimum ter-
mination height and with the appliance manufacturer’s 
installation instructions. (Fig. 45)
NOTE: Whenever DIRECT-TEMP penetrates through a 
ceiling, a floor or a wall, it must be firestopped.
12.  Using a level, make sure the system is perfectly 
vertical.
13.  Slide the flashing, suitable for the roof pitch, down 
over the pipe protruding through the roof. Recheck 
orientation and use a silicone sealant around and under 
the perimeter of the flashing where it is in contact with 
the roof. Secure the flashing with roofing nails. Finish 
roofing around the pipe, covering the sides and upper 
ares of the flashing base with roofing material. How-
ever, be sure the lower unnailed portion of the base 
covers the roofing material.
14.  Position the storm collar around the pipe and slide 
down until it is in contact with the flashing. Secure the 
storm collar by inserting the two (2) tabs into the raised 
slots and fold tabs back. Seal the area between the 
storm collar and the vent pipe with a silicone sealant to 
prevent rain infiltration.
15.  Install the vertical termination (VC) by inserting it 
down into the top most section of pipe until it is fully 
seated. Depress lock tab to secure the cap to the pipe. 
NOTE: In high wind areas, it is recommended to screw 
termination to the pipe with two (2) #8 x 1/4” sheet 
metal screws. The screws should be approximately 3/4” 
from the bottom of the vertical termination’s galvanized 
collar.
ST139
Radiance
remove front
4/20/01   djt
ST139
Fig. 46  Remove the stove front.
Install Log Set
Before beginning log installation, remove stove front 
and glass frame. Refer to Figures 44 and 47.
1.  Remove the logs from their packaging and inspect 
each piece for damage. DO NOT INSTALL DAM-
AGED LOGS.
ST141
pull glass latch
10/99 
ST141
Fig. 47  Release the latches to remove the glass frame.