Start-Up
Start-up checklist
Before starting the equipment, check to see that the following conditions are met:
•  All electrical connections comply with national and local codes and safety standards.
•  All accessories and ductwork have been installed.
•  Air flow to and from the equipment is not blocked.
•  The condensate drain is connected and not kinked or pinched.
How to apply power to the equipment
Insert the IEC-320-C19 connector of the power 
cord into the back of the equipment. Insert the 
opposite end of the power cord, a NEMA 5-20 
plug, into the wall outlet. Verify the circuit 
breaker is pressed in (flush with the rear of the 
equipment), and the green LED on the back of 
the plug is on.
Warning: Route the power cord and the condensate line to prevent accidental injury to 
people or damage to the equipment.
Circuit breaker
Electrical Hazard: Do not use 
extension cords with this 
equipment. Using an extention cord 
reduces circuit protection and voids 
the warranty.
Note: If the equipment has been 
unplugged or off for less than three 
minutes, it waits three minutes before 
starting the compressor.