Installation
Smart-UPS
®
 VT 
10-40 kVA 380/400/415 V with batteries
 10-40 kVA
 20-40 kVA without front panel
 10-15 kVA without front panel
 10-40 kVA from the rear
 10-20 kVA
 10-20 kVA without front panel
 10-20 kVA from the rear
IMPORTANT SAFETY INSTRUCTIONS
SAVE THESE INSTRUCTIONS
Warning: ALL safety instructions in the Safety Sheet 
(990-2822) must be read, understood, and followed when 
installing the UPS system. Failure to do so could result in 
equipment damage, serious injury, or death.
Warning: After the UPS has been electrically wired, do 
not start it up. Start-up is commissioned to APC-
authorized personnel only.
Caution: All electrical power and power control wiring 
must be installed by a qualified electrician, and must comply 
with local and national regulations for maximum power 
rating.
Note: Ensure that the unit is in its final location prior to 
installation.
Note: Battery and utility/mains power must not be 
connected until all other wiring has been completed.
Level the Enclosure
Warning: The system must be installed on a level floor. 
The leveling feet will stabilize the enclosure, but will not 
account for a badly sloped floor.
 Use a 13/14 mm wrench to adjust the four leveling feet. 
 Ensure that the system is level.
Caution:  Do not move the enclosure after the leveling feet 
have been lowered.
Floor Anchoring (if applicable)
Anchor the UPS enclosure to the floor
Note: Floor-anchoring bolts are not provided with the UPS. 
Purchase the bolts locally (minimum size: M8). Follow the 
specifications given by the manufacturer of the floor 
anchoring system when bolting the UPS system to the floor.
 Reuse the two transport brackets (one 
on each side) that were used to secure the 
UPS to the pallet during transport.
 Drill two to six holes in the floor for 
each bracket. Attach with bolts.