Verona VECTGMS304SS Istruzione Sull'Installazione

Pagina di 60
ENGLISH
Installation Manual
13
 
 
Pressure Testing 
The appliance must be isolated from the gas supply 
piping system by closing its individual manual shut-off 
valve during any pressure testing of the gas supply 
piping system at test pressures equal to or less than 
1/2 PSIG (3.5 kPa). 
This appliance, as well as its individual shut-off valve, 
must be disconnected from the gas supply piping sys-
tem during any pressure testing of the system at test 
pressures in excess of 1/2 PSIG (3.5 kPa). 
When checking appliance regulator function, make 
certain pressure of natural gas supply is between 6 
and 14 inches of water column or, if converted for LP 
gas, between 11 and 14 inches. 
 
THE PRESSURE TESTING SHOULD BE PER-
FORMED BY MEANS OF THE INJECTOR THREAD 
ZONE 
 
014
Figure 13.   
 
Pressure Test Method 

Remove grate and burner cap 

Remove aluminum gas spreader 

Temporarily remove the injectors 

Connect the pressure Test instrument into injector 
holder thread zone (M6x0,75) 

Check if the cooktop has the correct pressure 

Fix the injector removed for testing and replace 
the parts in the right position. 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Gas test inlet
Thread