In-Ground Plumbing Connections
IMPORTANT! Always check local codes prior to any in-ground spa instal-
lation. 
Once the spa and equipment are properly located, you will want to lay out 
the plumbing run.
Trenches should be deep and wide enough to allow all pipes to be buried 
below the frost line and should be in as straight a line from the spa to the 
equipment  as  possible.  Check  local  code  requirements  for  underground 
pipes. Always know what is under the ground before you dig anywhere.
You will need 2” flex or PVC lines for your suction, intake, and air line. In 
ground spas have marked intake and suction lines, making it easy find and 
connect to and from the spa and equipment pack.
The  plumbing  run  should  not  be  any  longer  than  15  feet  to  maximize 
water pressure. Another way to maximize water pressure is to limit (or 
even eliminate) the use of 90˚ elbows in your plumbing run. A more direct 
plumbing run using 45˚ elbows is more efficient, and promotes increased 
water pressure.
Identifying Plumbing Lines
The spa’s plumbing lines are clearly marked during water testing at the 
factory. This is done to assist installers in properly identifying the installa-
tion. We still recommend that the installers verify plumbing lines prior to 
gluing. This can be done by using one of the following techniques. 
Air Test
The  air  test  requires  a  wet/dry  vacuum.  Locate  the  plumbing  line  you 
wish to identify and secure the vacuum hose to cut open end. Turn on the 
vacuum, enter the spa and listen for vacuum suction sound from inside 
the spa side filter canister. If you hear the suction sound in the canister, 
the line is properly marked and can be connected to the suction side of the 
pump on the equipment pack.
Water Test
The  water  test  requires  a  garden  hose  and  water  source.  Locate  the 
plumbing line you wish to identify and secure the outlet side of the garden 
hose to cut open end. Turn on the water supply to the garden hose, enter 
the spa and look for water inside the spa side filter canister. If you see 
water in the canister the line is properly marked and can be connected to 
the suction side of the pump on the equipment pack.
If any plumbing line is not properly marked or not marked at all, follow 
either the air or water test procedure until all lines are identified prior to 
gluing.