DEFINITY Enterprise Communications Server Release 6
Installation and Test for Multi-Carrier Cabinets  
555-230-112  
Issue 5
May 1998
Install and Wire Telephones and Other Equipment 
Page 5-122
Add ISDN—BRI 
5
Add Circuit Packs
1. Determine port assignment of circuit packs to be added.
2. Install the appropriate circuit pack in assigned cabinet slot (as required). 
For example:
3. The TN778 Packet Control circuit pack and the TN556 
or
 TN2198 ISDN 
BRI circuit pack are required. Add the TN778 Packet Control circuit pack 
first. If an EPN is present, a TN570 Expansion Interface circuit pack is 
required.
4. The packet bus is required with BRI. If the system is not equipped with a 
packet bus see 
.
Install Cables
1. Install cables from cabinet to the MDF as required.
NOTE:
BRI requires a 12-port backplane cable terminator (breakout 
connector). Connect this terminator to the 25-pair cable. This is 
different from the 8-port connector used for DCP.
Power Up System
1. At each EPN, set the main circuit breaker to ON.
2. At the PPN, set the main circuit breaker to ON.
3. The system performs a level 4 reboot, loading the system translations from 
the translation card or tape. Rebooting takes several minutes.
4. After the system reboot is finished and all trouble is cleared, verify the 
EMERGENCY TRANSFER CONTROL switch is set to AUTO. This restores 
the system to the normal mode.
Enter Added Translations
1. Administer the required translation data using the forms listed under 
7500D voice terminals and 8500 voice terminals in 
DEFINITY Enterprise 
Communications Server Release 6 Administration and Feature 
Description
.
Port Number
3
B
02
01
Cabinet 
(Port Network)
Carrier
Slot
Circuit