* Note:  The power system settings only display 1400W of 
available power with two or three power supplies 
installed. A maximum configured switch requires a 
maximum of two power supplies. A third power supply 
may be added for redundancy in the event one of the 
other power supplies fails. All three power supplies will 
load-share during redundant operation. The remaining 
power supplies will share the full system load, in the 
event that the third power supply fails.
Displaying Cooling System Statistics
To display the switch’s cooling system status:
1. In the System Information section of the Web Agent window, 
click 
Cooling System. The Cooling System dialog box opens.
2. Ensure that all the individual components are operational by 
checking the status column for each component.
3. If a component’s status is non-operational, power down the Caju 
P880 Switch and contact a service representative to diagnose the 
failing unit.
Configuring Redundant Hardware
The Cajun P880 switch provides a redundant controllers and 
elements to ensure that if a controller or an element fails, the switch 
will continue to route data properly. The redundant components are 
available as separate options.
Total System 
Power
Displays the total system power in Watts.
Current 
Power 
Available
Displays the current power available.
Table 26.  Power System Statistical Parameters 
Parameter