Wiring the Power and Control Cables  
Power and control cables are routed through the bottom of the connection box through two strain 
relief bushings. 
Power cable entry
Control cable entry
Green ground wire 
connects here
 
Figure 4: Connection box – cable routing 
Wire the connection box according to Figure 5. Connections are described in detail in Table 1 on 
page 11. 
Control
cable
Power
cable
115 VAC
or
24 VAC/VDC
24VAC/DC S.B. - Pre-lube (pump off) mode
LL - Total lack of oil
PULSE - Drip indication
O.K
. - Sufficient lubrication
I
I
J
J
J
J
J
J
Voltage selector switch SW1:
115 VAC / 24 V AC/DC
Note: The pump can be optionally 
wired to shut down when the O.K. 
relay contacts open.
 
Figure 5: Connection box – electrical terminals: 115 VAC unit shown 
1.  Set the power switch SW1 located just below the transformer, for line power (115 VAC or  