Patterson-Kelley MACH-05 사용자 설명서

다운로드
페이지 59
  MACH®  Series
 
Gas-Fired Boiler 
Installation 
 
 
Page  9 
WARNING!  
Do not locate intake or exhaust terminations 
directly above a walkway; dripping of conden-
sation can cause icing of the walking surface.  
 
 
 
Reference: ANSI Z223.1 - 2002 
Sidewall Installations 
 
 
 
 
 
 
Rooftop Installations 
3.6.4  Vent Terminations 
 
 
 
 
 
 
 
Vent Termination Details 
 
 
The vent should extend at least three (3) feet above 
the roof, or at least two (2) feet above the highest part 
of any structure within ten (10) feet of the vent.  
To prevent the possible re-circulation of flue gases, 
your vent designer must take into consideration such 
things as prevailing winds, eddy zones, building 
configurations, etc.  P-K can not be responsible for 
the effects such adverse conditions may have on the 
operation of the boilers.  Dimensions listed above or 
those illustrated are minimum, and may or may not be 
sufficient for conditions at a specific job site. 
A tee must be of approved design and adequate 
capacity. 
 
3.6.5  Venting for Multiple Boilers 
The venting instructions in this manual apply to a 
single boiler.   
Venting systems for multiple boilers must be 
designed by qualified professionals and verified by 
the stack manufacturer.  The venting system must 
prevent backflow of exhaust gas through idle 
boilers which are not operating.  
 
 
No rain cap 
required, 
or Tee. 
Centering 
Support Plate
Sealant
Outside Plate 
Cover Plate 
Fastener 
Sealant 
12" min. 
Recommended 
Termination 
(see text below)
Mechanical draft vent 
terminal 
12 in. 
min. 
Direct vent terminal 
clearance minimum 12 in. 
12 in. 
min 
Mechanical draft 
vent terminal 
12 in. 
min. 
4 ft. 
min. 
Less 
than 
10 ft. 
4 ft. 
min. 
Forced 
air inlet 
3 ft min. 
Grade 
10' min. 
4' min. 
Flue Gas 
Outlet 
Combustion 
Air Inlet 
4' min above 
snow line