Ariston E-COMBI 24 30 38 Manual Do Utilizador

Página de 56
commissioning
29
First ignition operation
1. Check the electrical supply.
Complete  .  .  .  .  .  . 
Date   .  .  .  .  .  .  .  .  .  .  .  .
Installer  .  .  .  .  .  .  .  .  .  .
2. Check the type of gas and 
change the gas if necessary.
Complete  .  .  .  .  .  . 
3. Check the gas tightness.
Complete  .  .  .  .  .  . 
5. Check the exhaust fl ue. 
  See page 18
Complete  .  .  .  .  .  . 
6. Fill the installation.
  See page 30
Complete  .  .  .  .  .  . 
7. Check the hydraulic water 
tightness.
Complete  .  .  .  .  .  . 
8. Spin the pump.
Complete  .  .  .  .  .  . 
9. Set the heating power.
   See page 31
Complete  .  .  .  .  .  . 
10. Set up heating controls
Complete  .  .  .  .  .  . 
11. Balance the central heating 
circuit.
Complete  .  .  .  .  .  . 
12. Check the boiler in DHW mode
       (combi only)
Complete  .  .  .  .  .  . 
13. Adjust DHW fl ow rate on the 
boiler (if necessary).
Complete  .  .  .  .  .  . 
14. Analyse the combustion
       (see page 33)
Complete  .  .  .  .  .  . 
15. Check the ionisation current.
Complete  .  .  .  .  .  . 
16. Explain to the end user the the
       boiler operation.
Complete  .  .  .  .  .  . 
17. At the time of commissioning, complete all relevant sections of the 
Benchmark Checklist located on the inside back pages of this document.
Complete  .  .  .  .  .  . 
6. Measure the gas inlet pressure.
     standing + warming pressure
Complete  .  .  .  .  .  .