Install Telecommunications Cabling 
Page 2-49
Create a Provisioning Plan 
2
Create a Provisioning Plan
Determine an appropriate available port circuit on the system for each telephone, 
trunk, and peripheral connection needed, and, in addition, plan for auxiliary 
power for Basic Rate Interface (BRI) and certain display sets.
Create a Port Assignment Record to include the following. See 
Station or trunk type or feature/service
Building location (floor/room/desk/information outlet)
Extension number or trunk group and member number
Port circuit location on the system for each endpoint (cabinet/carrier/ 
slot/circuit)
Route from equipment room through equipment closets to each endpoint
Auxiliary power supply, if required