Install Management Terminal and Activate System 
Page 3-8
Activate the System 
3
DC-Powered System
1. At the DC Battery Cabinet (if installed), set the circuit breaker to ON.
2. At the DC Power Cabinet, set the circuit breaker(s) on the rectifiers ON. 
This starts the system initialization and test. Some red LEDs may be on but 
are turned off by other procedures in this chapter. 
3. If the system is high or critical reliability, power-up the EPN cabinet first, 
then the PPN cabinet. 
Always
 power up the PPN cabinet
 last
.
Verify Messages on Terminal
1. After several minutes, verify all tests pass. 
 displays the screen 
contents of a typical Release 6r system with 3 memory circuit packs. The 
Release 6si system screen is similar.
NOTE:
If any of the terminal messages indicate a test has failed or if the message 
spe down mode
” is displayed, refer to 
DEFINITY Enterprise 
Communications Server Release 6 Maintenance for R6r
, or 
DEFINITY 
Enterprise Communications Server Release 6 Maintenance for R6vs/si
, to 
clear the trouble.