Install and Connect Cabinets 
Page 1-4
Install System Cabinets 
1
Position the Auxiliary Cabinet (Optional)
1. Position the Auxiliary cabinet next to the PPN cabinet (or EPN cabinet, if 
installed). The location of equipment inside the Auxiliary cabinet is 
specified in the Customer Service Document (CSD).
2. If earthquake protection is required, skip to 
Installation’’ on page 1-34
. Return to this section when finished.
3. If earthquake protection is not required, level the cabinets and adjust and 
lock the cabinet stabilizing bolts to keep the cabinet from moving.
Install Auxiliary Cabinet Equipment
The Auxiliary cabinet allows for carrier, 23-inch (58.4 cm) rack, or panel 
mounting of hardware. The following equipment is furnished with the cabinet. 
Fuse panel 
— 
Distributes -48 VDC power to fused cabinet circuits
Power receptacle strip 
— 
Provides switched and unswitched 120 VAC 
receptacles
DC connector block 
— 
Required when Auxiliary cabinet is powered by an 
external DC source
AC to DC power supply 
— 
Converts AC power provided by the AC power 
strip switched outlet to the required DC voltage
1. Install equipment inside the cabinet as specified in the CSD. The following 
optional equipment can be installed:
Audichron H9040 Wake-Up Announcement System
909A/B Universal Coupler
7400 Series Data Modules
Z77A Multiple Data Mounting 
Fan Assembly 
— 
Requires 120 volt AC power
COMSPHERE 3000-series modems
External Channel Service Unit (CSU) 
— 
1 is required for each T1 
carrier link
PagePac Paging System 
— 
3 models are available. All PagePac 
models require 120 VAC power.