Lucent Technologies Release 6 Manual Do Utilizador

Página de 453
DEFINITY Enterprise Communications Server Release 6
Installation and Test for Multi-Carrier Cabinets  
555-230-112  
Issue 5
May 1998
Install Telecommunications Cabling 
Page 2-18
Cable Installation 
2
Cable Routing Guidelines
General
The following guidelines should be used when installing the equipment room 
cabling. Following these guidelines will maximize use of the cable slack 
managers and make future cabling additions and changes easier.
Figure 2-10
 and 
 show typical cable routing from the cabinet to the 
top and bottom of the MDF, respectively.
Figure 2-10.
Cable Routing to Top Terminal Blocks
Figure Notes:
1. Main Distribution Frame
2. AC Power Cord (AC-Powered 
Cabinets Only)
3. Cable Slack Manager Number 1
4. Trunk/Auxiliary Field
5. Station Distribution Field
6. Cable Slack Manager Number 2
7. Cable Slack Manager Number 3
8. System Cabinet(s)
9. To Building Cables
10. 10 AWG (#25) (6 mm
2
) Wire to 
Coupled Bonding Conductor
r758424b MMR 052996