Install and Connect Cabinets 
Page 1-3
Install System Cabinets 
1
Install System Cabinets
Check the location of the AC power receptacles in the equipment room. The 
receptacles must be on a separately fused circuit not controlled by a wall switch. 
They must be located within 10 feet (3 m) of the cabinet and outside the Main 
Distribution Frame (MDF) area.
Position the PPN Cabinet
1. If the system is supplied with cable ductwork, space the cabinets on 32 
inch (81.3 cm) centers +-1/8 inch (0.3 cm), they must be level, and must 
be square with respect to each other.
2. If the system is supplied with cable slack managers, place the cabinets far 
enough from the connection field to lay down the 32 inch (81.3 cm) slack 
managers and to provide a little extra room for the cables to access the 
cable slack managers.
3. If earthquake protection is required, skip to 
Installation’’ on page 1-34
.
4. If earthquake protection is not required, level the cabinets and adjust and 
lock the cabinet stabilizing bolts to keep the cabinet from moving.
5. At the bottom of the cabinet, install hole plugs (provided with cabinet) in 
the holes previously occupied by the 4 carriage bolts.
Position the EPN Cabinets
Each EPN cabinet is normally positioned adjacent to the PPN cabinet but may be 
located remotely in a different room or a different building.
1. The procedure for installing an EPN cabinet is the same as for the PPN 
cabinet.
2. If earthquake protection is required, skip to 
Installation’’ on page 1-34
.
3. If earthquake protection is not required, level the cabinets and adjust and 
lock the cabinet stabilizing bolts to keep the cabinets from moving.
NOTE:
To install a new EPN cabinet to an 
existing
 system, refer to 
DEFINTY 
Enterprise Communications Server Release 6 Upgrades and 
Additions for R6r
.