DEFINITY Enterprise Communications Server Release 6
Installation and Test for Multi-Carrier Cabinets  
555-230-112  
Issue 5
May 1998
Install and Connect Cabinets 
Page 1-20
Connect DC Power and Ground 
1
3. DC Power Cabinet Approved Ground
1. At the DC Power Cabinet, connect a 1 AWG (#70) (44 mm
2
) ground wire to 
the Ground Discharge Bar. See 
2. Route the ground wire out of the cabinet and terminate it on the approved 
ground. The approved ground must be identified with a grounding tag 
(FORM 15657NR or equivalent). See 
.
4. Connect Main AC Supply to DC Power Cabinet
1. Have a qualified electrician connect AC power leads to the rectifiers in the 
DC Power Cabinet. Each rectifier should have its own branch circuit. 
Terminate the leads on the AC INPUT terminal block of each rectifier.
2. Ensure the associated circuit breakers at the AC power panel are OFF.
5. Connect Ground Wires for DC-Powered 
Systems
!
CAUTION:
Do not connect any ground wires from an EPN cabinet to another EPN 
cabinet or to a PPN cabinet. All ground wires must be terminated at the 
single-point ground block at the main AC supply (AC mains).
1. Connect a 6 AWG (#40) (16 mm
2
) wire to the PPN cabinet ground terminal 
block. 
2. Route the wire to the AC mains single-point ground block and connect. 
3. Connect a 6 AWG (#40) (16 mm
2
) wire to each EPN’s cabinet ground 
terminal block.
4. Route the wire(s) to the AC mains single-point ground block and connect. 
6. Turn Circuit Breakers Off
The main circuit breaker on a DC-powered PPN/EPN cabinet is located on the 
front of the power distribution unit. The circuit breakers on the rear of the power 
distribution unit control the individual carriers. Se
 for the location of 
the carrier breakers.
1. Set the main circuit breaker to OFF.
2. Set the carrier circuit breakers to OFF.