Install Telecommunications Cabling 
Page 2-12
Install Cable Slack Managers 
2
Install Cable Slack Managers
1. Place the Z113A Cable Slack Manager against the wall under the MDF. 
See 
Figure 2-6
. Align the left side of the cable slack manager with the first 
terminal block of the trunk/auxiliary field.
2. Place the next cable slack manager beside the previously installed unit. 
Align the tabs and interlocks and snap the units together.
3. Repeat Step 2 until all cable slack managers are installed.
NOTE:
Nine 1/4-inch holes (0.63 cm) are provided in a cable slack manager 
base if earthquake mounting is required. If a base is mounted on an 
uneven floor, shims may be required for leveling and to assure 
proper fit of the covers. 
Holes are provided in the sides of the base for bolting cable slack 
manager together. Bolts and shims must be obtained locally.
4. The system cables will route through the cable slack manager as shown. 
Complete cable routing is covered later in this chapter.
Figure 2-6.
Cable Routing Through Cable Slack Manager
Figure Notes:
1. System Cabinet
2. Cable Slack Manager
3. Cable Clamp
4. Spare Center Troughs
5. Cabinet Trough for Port Cables
cbdfflr CJL 102396