Chapter 3 Installing the Library
Leveling the Library
Leveling the Library
24
Quantum|ATL 7100 Series Facilities Planning and Installation Guide
•
Digital voltmeter (DVM)
•
ESD protection kit
Leveling the Library
3
To level the library:
1
Move the library onto its designated footprint in the final
installation area.
installation area.
2
Lower each foot of the library until it makes contact with the
floor.
floor.
3
Moving in a clockwise direction from the library front, rotate
each foot clockwise so that each caster is raised approximately
1/4” off of the floor.
each foot clockwise so that each caster is raised approximately
1/4” off of the floor.
4
Center a carpenter’s level on the top front edge of the library.
5
Check the gauge on the level. If the front of the library is level,
proceed to step 6. If it is not level:
proceed to step 6. If it is not level:
a
Determine the tilt of the library and adjust the appropriate
front foot with the wrench, checking the gauge each time
that a foot is rotated ¼ turn.
front foot with the wrench, checking the gauge each time
that a foot is rotated ¼ turn.
b
Repeat step 5 until the front is level, then continue to the
next step.
next step.
6
Center the carpenter’s level on the top left edge of the library.
Note:
Completing this task involves leveling one side of the
library at a time, moving in a clockwise direction starting
at the front and ending with the right-side of the library.
library at a time, moving in a clockwise direction starting
at the front and ending with the right-side of the library.
Caution:
When adjusting the feet for leveling purposes,
DO NOT raise any foot so high that excess weight
is transferred to any single caster.
DO NOT raise any foot so high that excess weight
is transferred to any single caster.