Electronic Volume Corrector and Instrument Installation 
 
 
TDC-0824-003 100G Datalogging FN ERT Module Installation Guide - Remote Mount 
45  
 
Proprietary and Confidential 
 
 
 
 
3.  Dresser ROOTS IMC/W2 and MC2 cables are typically delivered with a cable tie installed. If the meter 
cable does not include a cable tie, install a tie to the cable just below the exposed colored lead wires on the 
cable insulation. Remove the excess cable tie using a hand-held sidecutter pliers. The cable tie performs as 
a cable strain relief to mitigate the risk of destructive tension on the lead wires.  
 
4.  Tuck the three gel connectors and cable tie inside the endpoint housing, as shown. Position the cable tie as 
shown by the arrow. 
 
 
 
5.  Install the 100G Datalogging FN remote ERT module backplate using the four screws previously removed 
from the ERT module and a Torx T-15 screwdriver.  
Important  Verify the cable tie and gel connectors are inside the module housing and the cable extends 
out of the slot in the backplate. Torque the backplate mounting screws to 9-12 inch-pounds.