Rack Installation
3-4 
Issue 1 October 1998
How to prepare the site for installation
Location
Checklist
Reference
Document
Installation
Requirements
DEFINITY ECS
Checklist
q
 
The maximum length of cable between the Rack
and the DEFINITY ECS is 500 ft (150 meters).
q
 
The Rack’s power supply and cabling should be
installed away from high power/high RF noise
devices such as computers, fans, fluorescent ballast,
power supplies, etc.
q
 
Use good wiring practices. Do not run wires over
fluorescent lights, computers, air conditioners, etc.
as this can introduce noise to the modems.
q
 
The Rack must be installed in a secure location.
Unauthorized access to the Rack could lead to toll
fraud.
Refer to the DEFINITY ECS Communications System
Generic 3, Installation for Single-Carrier Cabinets
manual, document #555-230-894, comcode
#107595423, for further information.
q
 
Four 25-pair cables with female connectors for each
Rack
q
 
One DCP line for each Model 3100 Switch Card
q
 
One analog line for each Model 3100 Switch Card
q
 
110-blocks sufficient for the installation
q
 
Additional cables sufficient for the DCP and analog
lines.
q
 
Install 110-blocks
q
 
Connect the DCP lines from the DEFINITY ECS to
the wall-field.
q
 
Connect two of the 25-pair cables to the Rack
digital ports (P106 and P108)
q
 
Cross-connect the Rack digital ports to the
DEFINITY DCP lines (see Tables 3-2 and 3-3 in
this Chapter)
q
 
Connect the analog lines from the PSTN or
DEFINITY ECS to the wall-field.
q
 
Connect the two remaining 25-pair cables to the
Rack  PSTN ports (P107 and P105).
q
 
Cross-connect the Rack PSTN ports to the analog
lines (see Tables 3-4 and 3-5 in this Chapter)