SharkRack Enclosure Installation Guide 
ID-00210-000 
REV D, ECO2773 
Page 6 of 46 
 
Chapter 1 Site Preparation 
 
Check Facility Provisions 
Ensure that the following conditions are met: 
•  Floor is level and of sufficient strength to support the rack and your equipment. At 
maximum gross weight, the floor must be able to support 1000 lb/in
2
.   
•  A qualified professional should complete site electrical power supply set-up. Ensure the 
types of outlets are consistent with the type of plugs on the power devices to be used. 
•  Check with a qualified HVAC technician to make sure the environment will support the 
heat load of the products being installed in the cabinet. 
•  Select a location for the cabinet that will allow adequate space for the door to open freely 
and slide-mounted equipment to be extended. 
•  Check that the site can accommodate the cabinet footprint and mounting locations 
according to the illustrations in Figure 3 and Figure 4.