Netgear M4300-52G (GSM4352S) - Stackable Managed Switch with 48x1G and 4x10G including 2x10GBASE-T and 2xSFP+ Layer 3 硬件手册

下载
页码 49
Installation 
40
Managed Stackable Switch Series M4300 
5. 
Tighten the screws with a No. 1 Phillips screwdriver to secure each middle mount.
6. 
Attach the supplied mounting brackets to the left side of the left switch and to the right side 
of the right switch.
7. 
Insert the screws provided in the rack-mount kit through each bracket and into the bracket 
mounting holes in the switches.
8. 
Tighten the screws with a No. 1 Phillips screwdriver to secure each bracket. 
9. 
Align the mounting holes in the regular brackets (on the left of the left switch and on the right 
of the right switch) with the holes in the rack, and insert two pan-head screws with nylon 
washers through each bracket and into the rack.
10. 
Tighten the screws with a No. 2 Phillips screwdriver to secure mounting brackets to the rack.
Step 5: Check the Installation
Before you apply power to the switch, perform the steps that are described in this section.
To check the installation:
1. 
Inspect the equipment thoroughly.
2. 
Verify that all cables are installed correctly.
3. 
Check cable routing to make sure that cables are not damaged or creating a safety hazard.
4. 
Ensure that all equipment is mounted properly and securely.