ENGINEERING STANDARD PROCEDURE 
IMPELLER INSTALLATION – TECH BULLETIN 
1of 1 
DOCUMENT NBR. : 
PED-017 
REVISION:  
EFFECTIVE 
DATE: 
09-16-2003 
 
 
 
0  
NEW 
UJB  
08-15-02 
1  
ADDED250LH 
UJB 
 
09-26-03 
REV ECN  CHANGE 
DESCRIPTION 
BY 
APPV’D 
DATE 
1.0 SCOPE:
 
 
 
Assembly Pre-Load / Bolt Torque requirements for Metric Fasteners of Grades A2-70 (304L) 
A4-70 (316L) and 8.8, for Sizes M4 to M20. 
 
2.0 METHOD: 
 
 
 
 
ASSEMBLY TORQUE / ASSEMBLY PRE-LOAD 
TIGHTENING TORQUE 
ASSEMBLY PRE-LOAD 
SIZE CLASS 
Nm lb/ft 
[lb/in] kN 
lbf 
M4 2.20 
1.622 
[19.46] 
2.73 
612.23 
M5 4.20 
3.097 
[37.16] 
4.47 
1002.44 
M6 7.40 
5.45 
[65.40] 
6.31 
1415.08 
M8 17.80 
13.12 
11.60 
2601.42 
M10 36.00 
26.54 
18.40 
4126.40 
M12 62.00 
45.72 
26.90 
6032.62 
M16 150.00 
110.62 
50.90 
11414.88 
M20 
A2-70, A4
-7
0,
 8.8 
303.00 223.45 82.00 
18389.40 
ABOVE TORQUE / PRE-LOAD VALUES ARE BASED ON A COEFFICIENT OF FRICTION OF 0.14 (Anti-seize Lubricant)